Site visit details

Overview

Catchment Dandenong
Site Jells Lake Landing ME_DJE200
Date and Time Friday 19th July 2019 10:30am
Approved Approved

Notes

Physical Chemical Tests

N mg/L NH4+ D.O. % D.O mg/L EC µS/cm pH pH Units rP mg/L P Air ° C Water ° C Turb NTU
Sample 0.2 82.14 9.2 230 7.6 0.07 12.6 10.3 15
Weather sunny
Last rainfall During the last 24 hours 2.00
Flow estimate
Water Appearance Muddy
Stream depth 51cm - 99cm
Stream width
Hazards
Litter/Pollutants polystyrene

Ammonium, Elecrical Conductivityand Reactive Phosphate are lower than last month, possibly due to 35mm rain in the last week. Still a lot of Ibis at Jells Lake.

Eye on water completed at 12.30pm.

Diary photos

No diary entries recorded for this visit

Creative Commons CC BY
All content, files, data and images provided by the Waterwatch Data Portal and Gallery are subject to a Creative Commons Attribution License

Content is made available to be used in any way, and should always attribute Waterwatch and www.vic.waterwatch.org.au